Dec 2016
More 2nd Floor Work
Sat, December 31, 2016
The photos in the gallery are from Tuesday Dec 28 and Saturday Dec 31. Work on the 2nd floor continues as they build the peaks for the roof.
Photo Gallery.
Photo Gallery.
2nd Floor Deck
Fri, December 23, 2016
1st Floor Begins
Tue, December 20, 2016
The first floor is taking shape and the ceiling is being constructed for the second floor.
Photos here...
Photos here...
Walls Up!
Sat, December 17, 2016
Electrical
Wed, December 14, 2016
Met with the appriser and at the same time was able to catch the electrical conduit trench. There’s also a photo of the trench to the well.
Photos here.
Photos here.
Foundation Complete & Framing Begins
Mon, December 12, 2016
Last week the foundation construction was completed. This included adding the moisture barrier and footing drainage system. After the Building Inspector reviewed the progress the drainage was covered in stone and a fabric mesh and the foundation was backfilled. The site was also graded with the remaining material. More stone was brought in and the basement was filled as well as the basement stairwell.
This past weekend in anticipation of the upcoming snow forecast for Monday the framing began. The crew was able to frame the subfloor and get it covered before the snow.
Photos of the final steps to the foundation are here.
Photos of the framing are here.
This past weekend in anticipation of the upcoming snow forecast for Monday the framing began. The crew was able to frame the subfloor and get it covered before the snow.
Photos of the final steps to the foundation are here.
Photos of the framing are here.