Foundation Complete & Framing Begins
Mon, December 12, 2016
Last week the foundation construction was completed. This included adding the moisture barrier and footing drainage system. After the Building Inspector reviewed the progress the drainage was covered in stone and a fabric mesh and the foundation was backfilled. The site was also graded with the remaining material. More stone was brought in and the basement was filled as well as the basement stairwell.
This past weekend in anticipation of the upcoming snow forecast for Monday the framing began. The crew was able to frame the subfloor and get it covered before the snow.
Photos of the final steps to the foundation are here.
Photos of the framing are here.