2nd Floor Cove & Baseboard
Fri, April 21, 2017
The second floor trim is nearly complete. The cove moulding has been installed from the stair landing down the hallway to the master bedroom. All that remains is the baseboard in the master and rear bedroom.
Outside the propane tank and gas line has been inspected and backfilled. Mike is also in the process of finalizing the lawn/yard to its finish grade
Looking snazzy...
Outside the propane tank and gas line has been inspected and backfilled. Mike is also in the process of finalizing the lawn/yard to its finish grade
Looking snazzy...