Boards delivered
Wed, February 22, 2017
Today lot’s of different board was delivered. The plaster board was delivered and stacked in all the rooms. Also delivered was the material for the front porch, mahogany slats for the deck and stair treads as well as the cedar posts. The rough electrical is now complete including a set of pipes that run from the basement to the attic for future running of wire (very nice suggestion). The exterior siding is also nearing completion.
After touring the house John and I walked the neighborhood loop - approx. 1 mile - not too shabby.